AIA Contracts CE – 003

1 / 10

During review of a contractor’s submittal for a specified HVAC unit, the architect discovers that a substitution was made. The substitution was not submitted separately nor approved in advance by the architect.

What should the architect do?

2 / 10

Who confirms that the requirements of the contract have been met before final payment is certified?

3 / 10

Which of the following may be included in the contractor’s final application for payment? Check the four that apply.

4 / 10

When is retainage typically released to the contractor under AIA A201?

5 / 10

Which of the following must be defined in the G704 Certificate of Substantial Completion?

6 / 10

While reviewing the contractor’s schedule of values for a renovation project, the architect notes that several line items combine multiple scopes of work under single cost categories. The architect is concerned that this may lead to inaccurate progress evaluations during monthly pay application reviews.

What should the architect do first?

7 / 10

What must occur before the one-year correction period begins under AIA A201?

8 / 10

Which document formally requests final payment after the architect confirms completion?

9 / 10

Which of the following are required for the contractor to receive final payment under A201? Check the three that apply.

10 / 10

A contractor completes roofing work and submits a pay application with supporting photos. During the site visit, the architect observes incomplete metal flashing and loose cap sheets.
Which of the following are appropriate next steps for the architect? Check the three that apply.

Your score is