III
1 / 10
Which of the following statements about Construction Change Directives (CCDs) are true?Check the two that apply.
Explanation:They allow work to proceed when cost/time are not yet agreed uponA201–2017 §7.3 defines CCDs as tools to maintain schedule while awaiting pricing agreement.
They are signed by the owner and architect onlySince the contractor has not agreed to pricing, only the owner and architect sign the CCD.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.6 Use contractual tools for time-sensitive work
2 / 10
During bidding, a contractor submits a request to use an alternate mechanical unit not listed in the specs. The request is received three days before the bid opening.What should the architect do?
Explanation:Under A701–2018 §3.3.2, substitutions must be submitted at least 10 days before bid date unless otherwise permitted. Late substitutions are not considered.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.2 Evaluate bid phase processes
3 / 10
Which of the following documents are typically included in the project manual for bidding purposes?Check the three that apply.
Explanation:Instructions to BiddersA701–2018 provides bidders with procedures and requirements for bid submission.
Specifications (Divisions 00–49)The technical specs are essential for defining materials and workmanship.
Bid FormStandardized bid forms ensure consistent pricing submission formats.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.4 Identify appropriate construction document components
4 / 10
An owner instructs the architect to issue clarifications via email directly to a preferred bidder to accelerate bidding.What should the architect do?
Explanation:A701–2018 §3.4.3 requires all clarifications be distributed as addenda to ensure fair competition. Selective communication creates ethical and legal issues.
5 / 10
Which event must occur before the construction start date under the Stipulated Sum agreement?
Explanation:The contract must be executed (A101–2017 Article 1) before construction starts, defining scope, payment, and schedule terms.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.3 Execute owner–contractor agreements
6 / 10
A contractor submits a bid containing an alternate not listed in the bidding documents. The bid amount is significantly lower than others. What is the architect’s responsibility?
Explanation:Per A701–2018 §4.2.1, bids not conforming to requirements may be rejected. The architect advises the owner but does not unilaterally disqualify a bidder.
7 / 10
The project team selects the Construction Manager as Constructor (CMc) delivery method. What impact does this have on preconstruction roles?
Explanation:In CMc delivery, the constructor participates during design to advise on cost and constructability (AIA A133–2019 §3.2), working collaboratively with the architect and owner.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.1 Evaluate project delivery methods and impact
8 / 10
During pre-bid RFI review, the architect receives a question indicating a discrepancy between the structural and architectural drawings. What should the architect do?
Explanation:Per A701–2018 §3.4.3, clarifications must be issued via addenda to all bidders prior to bid opening to maintain fairness and consistency.
9 / 10
During the design phase, the owner adds a rooftop amenity deck not included in the initial scope. What is the most appropriate next step for the architect?
Explanation:Per B101–2017 §4.3, substantial scope changes initiated by the owner may warrant additional services. The architect must document and seek agreement on compensation.
Topic: Construction & Evaluation → Section 1: Preconstruction Activities → 1.5 Evaluate scope changes and additional services
10 / 10
Which of the following are the architect’s responsibilities during the bidding phase?Check the two that apply.
Explanation:Responding to bidder RFIsThe architect provides clarifications about the bidding documents.
Issuing addenda clarifying design intentPer A701–2018 §3.4.3, the architect must issue formal addenda as needed.
Your score is
Restart quiz