AIA Contracts CE – 007

1 / 10

While reviewing a contractor’s application for payment, the architect notices that stored materials listed on the G703 continuation sheet are located off-site. What must the architect confirm before certifying payment?

2 / 10

Under A701–2018, what is the proper response if a bidder discovers an error in their bid immediately after opening?

3 / 10

Which of the following may lead to issuance of a Construction Change Directive (CCD) rather than a Change Order?

4 / 10

A contractor identifies a concealed condition during demolition that was not shown in the construction documents. What should the architect do first?

5 / 10

Which of the following should be included in the final project closeout documents submitted by the contractor? Check the four that apply.

6 / 10

A subcontractor disputes the architect’s rejection of its shop drawing and contacts the owner directly. How should the architect proceed?

7 / 10

A consultant reviews submittals related to their discipline and approves a substitution without informing the architect. According to C401–2017, what is the appropriate course of action?

8 / 10

Which of the following statements reflect responsibilities of the architect during the one-year correction period? Check the two that apply.

9 / 10

The architect issues a Certificate for Payment, but shortly after, discovers that work certified was not actually complete. What is the architect’s next step under AIA A201–2017?

10 / 10

During closeout, the owner requests a delay in issuing substantial completion to extend the contractor’s liability. What is the architect’s obligation under AIA A201–2017?

Your score is