III
1 / 10
A contractor fails to protect glass doors during steel grinding work, damaging one door. The specifications require protection of adjacent finishes but do not explicitly mention glass. The contractor agrees to replace the damaged glass but submits a change order for the cost of installing plywood protection over all remaining doors. How should the architect proceed?
Explanation:A201–2017, §3.3.1 assigns responsibility for protection and means/methods to the contractor. The CCD allows work to proceed while preserving the owner’s right to dispute cost.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.2 Evaluate and respond to changes in the work
2 / 10
During a punch walk, the architect finds nonconforming work: damaged ceiling tiles, malfunctioning light fixtures, and loose rubber base. The architect needs to document and initiate corrections. What is the most appropriate next step?
Explanation:AIA A201–2017, §12.1.1 requires the architect to document and reject nonconforming work. A field report officially records these items for resolution.Topic: Construction & Evaluation → Section 4: Project Closeout & Evaluation → 4.1 Develop a punch list
3 / 10
An architect observes that the sheet vinyl installed in the main corridor of a condominium project appears warped and moist. The contractor claims the product was stored and installed according to the manufacturer’s instructions, and the vinyl cost is listed as $10,000 in the pay application. What should the architect recommend?
Explanation:Withholding payment is appropriate when there is reasonable evidence that installed materials may not meet contract standards. AIA A201–2017, §9.5.1.1 permits the architect to withhold certification for payment when defective work is suspected.Topic: Construction & Evaluation → Section 2: Construction Observation → 2.1 Evaluate construction for conformance
4 / 10
A tenant requests to replace the ceramic tile finish in their condo unit three days after the originally specified tile has already been installed. The contractor submits a change order to the developer for the rework and material cost. Which parties are responsible for the change costs? Check the two that apply.
Explanation:The tenantThe tenant requested a post-installation change, so they are financially responsible for the revised material and labor.The contractorThe contractor is entitled to be compensated for the rework, which was done at the tenant’s request after the original installation.Topic: Construction & Evaluation → Section 2: Construction Observation → 2.2 Evaluate and address nonconforming work
5 / 10
The general contractor is delayed by 21 days: 14 due to construction errors and 7 due to owner changes. The contract includes liquidated damages of $15,450 per day. What is the total amount of liquidated damages the contractor is responsible for?
Explanation:Only the days attributable to construction errors (14 days) are chargeable to the contractor: 14 x $15,450 = $216,300.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.5 Interpret project schedule delays and damages
6 / 10
During review of the G703 Continuation Sheet, the architect notes that retainage values are missing. The contract stipulates 10% retainage on hard costs and 5% on overhead and soft costs. The schedule includes $7,600 for general conditions, $1,950 for performance bond, $2,200 for concrete repairs, $1,750 for masonry repairs, and $6,000 for engineering services. What is the correct total retainage amount?
Explanation:The correct total is calculated as follows:(5% of $7,600) + (5% of $1,950) + (10% of $2,200) + (10% of $1,750) + (5% of $6,000)= $380 + $97.50 + $220 + $175 + $300 = $1,172.50Refer to AIA A201–2017, §9.6.1 for retainage withholding.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.3 Evaluate payment applications
7 / 10
The mechanical subcontractor submits a submittal that omits the required physical product sample for ceramic tile. The architect is working on an accelerated schedule. Which responses are appropriate for the architect to issue? Check the two that apply.
Explanation:Review the compliant portions of the submittal and note the missing sampleA201–2017, §3.12 allows partial review of submittals to keep the project moving.Request the contractor to submit the physical sample before full approvalThe missing sample must be provided and approved before installation, but the rest of the submittal can be processed.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.1 Review submittals
8 / 10
A contractor submits a concrete materials submittal with a substituted floor sealer that was not reviewed properly. Later, during tile installation, the tile adhesive proves incompatible with the sealer. The contractor submits a claim for extra time and cost. How should the claim be resolved?
Explanation:Per A201–2017, §3.12.4, substitutions must be clearly identified and separately submitted. Burying a substitution within a larger submittal does not relieve the contractor of responsibility.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.1 Review submittals
9 / 10
During construction, a fire breaks out at the project site, damaging partially completed framing. The owner threatens to sue the contractor and architect, though A201–2017 requires the owner to carry property insurance during construction. Which insurance is contractually responsible for covering the damage?
Explanation:AIA A201–2017, §11.4.1 requires the owner to maintain property (builder’s risk) insurance for the project during construction to cover such losses.Topic: Construction & Evaluation → Section 3: Administrative Procedures & Protocols → 3.4 Interpret contractual and insurance requirements
10 / 10
While performing a punch list before certifying substantial completion, the architect observes several deficiencies. Which items must be corrected before the building can be deemed substantially complete? Check the three that apply.
Explanation:Missing handrails along one side of a stairHandrails are required for safe egress and occupancy and must be in place before substantial completion.Non-functional toilet in a residential unitBasic plumbing fixtures must be operational for a residential unit to be considered habitable.Missing smoke detector in a bedroomSmoke detectors are life safety equipment and essential for occupancy certification.Topic: Construction & Evaluation → Section 4: Project Closeout & Evaluation → 4.1 Develop a punch list
Your score is
Restart quiz