AIA Contracts CE – 002

1 / 10

Which contract form is most appropriate for authorizing a minor change in the work with no cost or time impact?

2 / 10

According to AIA A134–2019, who is responsible for preparing and maintaining the construction schedule?

3 / 10

What must the architect do before certifying an Application for Payment per AIA A201–2017?

4 / 10

The architect arrives on site and observes that the contractor is installing HVAC ductwork not shown in the approved shop drawings. What should the architect do first?

5 / 10

According to AIA G709, what is the primary purpose of a Work Change Proposal Request?

6 / 10

During construction, the contractor submits a shop drawing that deviates from the contract documents. According to AIA A201–2017, what is the architect’s most appropriate action?

7 / 10

Under AIA A701–2018, who is responsible for issuing Addenda during the bidding process?

8 / 10

Under A201–2017, what is the architect’s responsibility when conducting site visits?

9 / 10

Which of the following are architect responsibilities during the submittal review process per AIA A201–2017? Check the three that apply.

10 / 10

A contractor submits a substitution request during the submittal phase. According to A201–2017, how should the architect proceed?

Your score is