AIA Contracts CE – 006

1 / 10

Which of the following are appropriate actions by the architect during project closeout? Check the three that apply.

2 / 10

During a project under the A101–2017 contract, the contractor includes an unapproved alternate in the pay application. The architect discovers this during their review. What should the architect do?

3 / 10

The contractor has completed work on the HVAC system but the commissioning report indicates airflow is 15% below specified values. The contractor requests payment for the mechanical work. What should the architect do?

4 / 10

The contractor submits a request for time extension due to unusually severe weather. The owner asks if this qualifies as a valid delay under the contract. What should the architect reference?

5 / 10

During review of the G702 payment application, the architect notices that retainage is being calculated inconsistently between trades. The contractor says this is to help cash flow on labor-intensive trades. What should the architect do?

6 / 10

During construction, the contractor finds a buried fuel tank not shown in the documents. They immediately notify the owner but take no further action. The owner asks the architect to instruct removal. What is the most appropriate next step?

7 / 10

Which items are required for processing a valid Change Order using G701? Check the two that apply.

8 / 10

The contractor submits a pay application that includes stored HVAC equipment at an off-site warehouse. The owner is concerned about releasing funds before the units are installed. What should the architect do before certifying this portion of payment?

9 / 10

A consultant refuses to respond to a contractor’s submittal, claiming it is the architect’s responsibility. The architect, in turn, is unsure whether this submittal falls within the consultant’s scope. What should the architect do?

10 / 10

The contractor notifies the architect that a door hardware supplier missed a finish specified in the contract. The contractor proposes an alternative with a similar finish but different performance rating. What should the architect do?

Your score is